Projects

Indianola Community School District Projects

DCI Group has performed construction management agency services for the Indianola Community School District for several recent and ongoing projects. This includes recently completed projects at Whittier Elementary, Irving Elementary and two phases of a three phase Stadium project. Preconstruction efforts for all projects are complete and construction phases for Emerson Elementary, High School Addition and Renovation, and the final phase of the Stadium were completed in late 2015. These projects involved extensive interior demolition and remodel
to improve classroom and support spaces. The projects have very aggressive timelines to maintain school operations and some work is being conducted under occupied conditions. The preconstruction effort was conducted over 16 months and involved the building and execution of 9 different project bid documents.

PROJECT CHARACTERISTICS

  • DCI Group Construction Manager
  • $29 Million Construction Cost
  • Multiple Prime Contractor
  • Renovation
  • Commissioning Agency Procurement
  • Completed Under Very Aggressive Timelines

SCHOOL PROJECTS

Whittier Elementary

Complete mechanical, electrical, architectural, and site renovations to a 56,000 square foot public elementary school facility, and the construction of mechanical room, classroom additions as well as a new Media Center addition with ancillary support spaces. Project completed under two separate phases allowing Owner to partially occupy during construction. Construction started March 2014 and substantially complete January 2015. Total Project Budget: $9,000,000

Irving Elementary

Entire site renovation, adding new off street parking, expanded and enhanced playgrounds. The building received new secure entries along with a new addition for teacher and student access. Interior classrooms and offices had minor renovations. Construction started March 2014 and substantially complete October 2014. Total Project Budget: $3,600,000

Emerson Elementary


Complete mechanical, electrical, architectural, and site renovations to a 54,000 square foot public elementary school facility. Project completed under two separate phases allowing Owner to partially occupy during construction. Construction started January 2015 and substantially complete December 2015. Total Project Budget: $7,600,000 

Stadium Improvements

Two new parking lots adding around 500 stalls were constructed.  A 3,000 seat Bleacher and Pressbox structure was built on the west side of the existing track to serve as the home stands.  A large Team Building and separate Concession Building were built to the north of the existing track/football field. There was a large site work scope involved with all three of these Phases. Construction started September 2013 and substantially complete November 2015. Total Project Budget: $6,000,000

High School Improvements

Multi-phased project that began with replacing all interior/exterior door hardware.  New building addition for Family Consumer Science followed by a complete interior gut and remodel for Administration Offices, Guidance Offices, and Professional Development meeting space for the school district.  Construction started January 2014 and substantially complete January 2016. Total Project Budget: $2,800,000

 

 

 

 

 

 

Indianola Community School District ~ Indianola, Iowa

This entry was posted in Completed Projects. Bookmark the permalink. Follow any comments here with the RSS feed for this post. Both comments and trackbacks are currently closed.