Interstate-35 CSD Renovation & Additions

DCI Group is providing Construction Management services to complete two projects for the Interstate-35 Community School District. DCI is currently progressing through construction and preconstruction phases of these projects. Significant renovations and additions to the K-12 building are planned. Construction of the new CTE Maintenance Building began in June of 2017. This entails a 15,000SF pre-engineered metal building to house the new wood and metal shop with classroom space and an area for the school’s maintenance staff and supplies. The next phase of construction will include converting the current wood & metal shop space into the fine arts department with space for choir, high school and elementary band practice rooms, and staff offices. A 600-seat auditorium will be added for the fine arts productions and community events. These projects are taking place during occupied conditions, so strict logistics planning is required. Work at I-35 Schools is scheduled to be completed in Summer 2019.

PROJECT CHARACTERISTICS

  • $15 Million Total Construction Cost
  • DCI Group Construction Manager
  • Multiple Prime Contract
  • Assisted in Master Plan/Design Process
  • Procore Software Utilization

 

 

I-35 Community School District ~ 405 E North St., Truro, IA

Comments Off on Interstate-35 CSD Renovation & Additions

Beardsley Regional Stormwater Detention

The Beardsley Regional Stormwater Detention Facility for the City of Norwalk consists of mass grading and drainage improvements. There are two permanent pool detention ponds including the following: approximately 174,100 cubic yards of excavation, impervious clay seal, hauling and spreading excess excavation of approximately 156,000 cubic yards on adjacent commercial properties, approximately 78 linear feet of 6-foot by 6-foot RCBC, 68 linear feet of 8-foot by 5-foot RCBC, 6 linear feet of 42-inch RCAP, 9 RCP culverts varying from 15-inch to 24-inch diameter in open cut with area intakes, 9 manhole adjustments, 6 spillway structures, outlet structure, excavation, backfill, gabion lined drainage swales, rip-rap, erosion stone, erosion control, surface restoration, mobilization, traffic control, and miscellaneous work including cleanup. Development of Turnberry Road connecting Highway 28 to Colonial Drive is also planned for April 2017.

PROJECT CHARACTERISTICS

  • $2,329,682 Construction Cost
  • City of Norwalk Project
  • Future Plans Including Development of Turnberry Road and Commercial Lots

Comments Off on Beardsley Regional Stormwater Detention

Prairie City Monroe Community School District Projects

DCI Group is providing Construction Management services to complete three projects for the Prairie City Monroe Community School District. DCI Group has provided pre-bond referendum and is currently progressing through construction and preconstruction phases of the projects. Significant renovations and additions to the Middle School and High School are planned, as well as major renovations to Monroe Elementary School. These projects are taking place during occupied conditions, so strict logistics planning is required.

PROJECT CHARACTERISTICS

  • $20 Million Total Construction Cost
  • Monroe Elementary Renovation – $3 Million
  • Prairie City Elementary/Middle School Addition/Renovation – $9 Million
  • High School Addition/Renovation – $8 Million
  • DCI Group Construction Manager
  • Multiple Prime Contractor
  • Pre-Bond Referendum Cost and Scheduling Consultation
  • Commissioning and Testing Agency Procurement

 

Prairie City Elementary, 309 E Plainsman Rd, Prairie City, IA 50228 ~ Monroe Elementary, 400 Jasper St, Monroe, IA 50170 ~  PCM High School 400 E HWY 163, Monroe, IA 50170

Comments Off on Prairie City Monroe Community School District Projects

Detention Facility Projects

ICIW BUILDING Y ADDITION

This project is currently in progress with an anticipated completion date of January 2017. It includes an addition to Building Y on the ICIW campus incorporating a cafeteria and classroom space.

IOWA STATE PENITENTIARY HUMIDITY CONTROL

We are currently completing construction documents for improvements related to humidity control on several buildings on the new campus. This project is scheduled to be complete late this year.

IOWA STATE PENITENTIARY JOHN BENNETT SKYLIGHT REPLACEMENT

Complete removal and replacement of large dayroom skylight in the John Bennett building. Project was on schedule in June 2016 while inmates occupied the space.

IOWA JUVENILE HOME MULTIPLE PROJECTS

DCI Group has completed several projects at the Iowa Juvenile Home in Toledo between 2011 and 2013. This includes security upgrades, fire alarm replacements, security electronics, water, sewer, and site concrete improvements.

OTHER RELATED PROJECTS

  • Iowa State Patrol Post #1 site improvements
  • Iowa Veterans Home campus wide security cameras
  • Major maintenance improvements at Anamosa State Penitentiary, Clarinda Correctional Facility, Clarinda Mental Health Facility, Glenwood Resource Center, Eldora Training Center, Independence Mental Health Facility

     

    Comments Off on Detention Facility Projects

    220 SE 6th Street Office Building & Parking Ramp

     

    As the Construction Manager at Risk, DCI Group is managing the construction of a 50,000 SF precast office building and four story precast parking structure. This project is on a green field urban site. In addition to the office and parking structure, DCI Group is also paving Elm Street and performing public improvements for the City of Des Moines which will be turned over at the end of the project. This project also includes the finishing of four tenant spaces in the building. DCI Group is also involved in the furniture selection and procurement for each tenant.

     

    Project Characteristics

    • $12M Combined Cost
    • Construction Manager at Risk
    • Multiple Prime Construction Model
    • Assisted in Master Plan and Design Process

     

    220 SE 6th Street, Des Moines, IA 50265

    Comments Off on 220 SE 6th Street Office Building & Parking Ramp

    Principal Corporate 1

    The Principal Financial Group Corporate 1 Renovation involves approximately 475,000 SF of renovation work. It began in May of 2015 and is scheduled to be complete in mid 2017. The renovation work includes 7 floors of extensive interior demolition and the build back of corporate office, conference centers, wellness, atrium, auditorium, pavilion and cafe. The work also includes major revisions and improvements to mechanical, electrical and plumbing systems, exterior façade, roof replacement and a new skywalk connection across High Street. The Corporate 1 building was built in three additions- 1939, 1959 and 1976. This is the only project on the Principal campus that will be completely vacated during construction, as this building will be taken back to the bones and rebuilt.

    PROJECT CHARACTERISTICS

    • DCI Group Construction Manager Agent
    • $148 Million Construction Cost
    • Multiple Prime Contract Model
    • Led the Master Plan and Design Process
    • Renovation
    • Sustainability Practices Followed
    • Schedule Duration Critical with Move Management
    • Commissioning and Testing Agency Procurement
    • Extensive Mechanical, Electrical, and Plumbing Scope

    Click here to read about Chris Conn, the Senior Superintendent on the Corp 1 project who was featured in an article on Principal Financial Group’s internal network showcasing the work he has done on the downtown campus renovation!

    Principal Financial Group ~ 711 High Street, Des Moines, Iowa

    Comments Off on Principal Corporate 1